Don Muang Airport to continue to serve domestic & charte

Local Hua Hin and regional Thailand news articles and discussion.
Post Reply
Norseman
Rock Star
Rock Star
Posts: 4665
Joined: Tue May 10, 2005 12:13 pm
Location: Hua Hin

Don Muang Airport to continue to serve domestic & charte

Post by Norseman »

From the TNA News.

Caretaker Transport Minister Pongsak Raktapongpaisal said here on Saturday that the existing facilities at Bangkok's Don Muang International Airport would continue to cater to domestic and chartered flights after the opening of the new Suvarnabhumi Airport scheduled for late July this year.

Turning down a proposal made by the board of Thai Airways International Public Company Limited (THAI), which requested that the Don Muang International Airport should be closed after the commercial opening of the Suvarnabhumi Airport, Mr. Pongsak said it is the government's policy to continue using both airports as it would create more advantages for the country.

He said that it was up to THAI to determine how to operate its office at Don Muang.

Progress regarding the exact date of the opening of the Suvarnabhumi Airport would be announced to the public later as Airports of Thailand Public Co., Ltd. (AOT) is entirely responsible for the construction, he said, adding that the new airport would be opened for commercial purposes in late July as announced earlier.

So far more than 60 items, including the runways, passenger terminals, luggage scanning equipment and passenger check-in systems, are now complete and ready for operations, he noted.


Then from Bangkok Post.



New airport'will not be open in July'
Construction delays, cost increases blamed


AMORNRAT MAHITTHIROOK

The contractor has admitted that Suvarnabhumi airport cannot open in July, as caretaker Prime Minister Thaksin Shinawatra announced, due to delays in construction and cost increases. A source at the Transport Ministry said the new airport could not meet the July opening schedule because many construction jobs were delayed, which held up operational tests.

To speed up construction, parties responsible for the project intend to divert over 40 construction contracts to fast outsourcing, without open bidding contests. The practice could lead to favours of specifications for particular contractors, the source said.

''All parties know that the airport cannot open this July but no one dare speak out, fearing that it could deal a blow to Mr Thaksin, who made the announcement.

''If the opening was postponed until December, those 40 contracts would be subject to open bidding contests,'' the source said.

Many airlines had expressed concern over the delay and doubted the airport would open in July, the source added.

A source in ITO Joint Venture, the constructor of the airport, said it needed another three to four more months to finish work and officials responsible for the project were already aware of the situation.

A source at Airports of Thailand Plc (AOT) said that, apart from delayed construction, ITO Joint Venture was demanding an additional six billion baht from AOT for increasing construction work at the new Bangkok airport.

The joint venture led by Italian-Thai Development Plc said it had to do more work than specified in its original contract but AOT has not agreed to the additional sum. The dispute is also delaying completion of the airport.

According to the source, more construction work was assigned because the government wanted to increase the capacity of the new airport from 30 million passengers a year to 45 million.

Higher costs of raw materials also add to the dispute.

To settle the issue, AOT asked a committee of outsiders to examine the additional construction work and compared the cost claim with market prices.

The committee consists of representatives from the Engineering Institute of Thailand, the Association of Siamese Architects, the Council of Engineers, the Office of the Attorney-General, the Comptroller-General's Department and the ministries of transport and commerce.

Earlier the joint venture demanded an extra two billion baht, but the AOT approved only 600 million baht. The final additional cost should not reach the six-billion-baht claim, the source said.

The original cost of the new airport stood at 120 billion baht.

Suvarnabhumi airport director Somchai Sawasdeepon said verification of the extra money claimed would delay the airport's opening but careful consideration was worth the time.

However, caretaker Transport Minister Pongsak Raktapongpaisal insisted yesterday that the airport could open in July and Don Muang airport would close at that time.

He said luggage conveyors and scanners next to the western runway have been tested, but the tests for those near the eastern runway had just started. The tests will be completed next month.

Signalling systems for aprons and taxi-ways have been tested and the airport hotel will open next month when the public will be welcomed to visit the new airport, he said.

The roofing of the concourse buildings will be replaced in June simultaneously with repairs to leaks in the roof of the airport information management system building.

Tests of aircraft refuelling systems will start next month
I intend to live forever - so far so good.
User avatar
PeteC
Moderator
Moderator
Posts: 32343
Joined: Tue Mar 23, 2004 7:58 am
Location: All Blacks training camp

Post by PeteC »

It's January 4, 2008 and I'm just returning from a Christmas visit to my family in the States, and landing at Don Muang. Pete
Post Reply